645 F.3d 978
Environmental organizations brought action against Amry Corps of Engineers, Fish and Wildlife Service, and electric utility for violating the Clean Water Act (CWA), National Environmental Policy Act (NEPA), and Endangered Species Act (ESA) in the process of obtaining a permit to construct a new coal-fired power plant. Preliminary injunctions were granted in part and permit work was ordered to halt. Utility appealed.